Strawbale Building in Golden

Tuesday, September 26, 2006

Progress, Progress

OK, so I'm not a prolific blogger. The house is humming away.
On Labor Day, while finishing dinner with Kenny and Kristi, Keith informed the group that we would be pouring the basement floor on Saturday, September 9. This seemed odd to me because I thought the radiant in-floor heating tubing had to be installed before the concrete could go in and there was no tubing to be seen. Well, it did and on Wednesday (after 24 hours of call and no sleep) I arrived at the job site and found Keith and Chuck standing in the garage discussing the two boxes of tubing sitting on the floor. Now, some of you may think that two full days would be plenty to lay tubing in 1,800 square feet but the floor had to be inspected on Friday before the pour could occur.
While I went home (to the basement) to sleep, Al, Ben, Nick, Chuck, Kenny, Kristi, and Mary joined Keith for a tubing layout fiesta. The work continued all day Thursday and by Friday night, the inspection had been done and the site was ready for the pour.
On Saturday, September 9, Roberto, Jesus and their helpers arrived a 7 a.m. and prepared for the first load of concrete. The pour was going beautifully until 11:30. Clouds were building, so Keith, John and I were on the second floor preparing a tarp, just in case it rained. At noon, the skies opened and we had the hardest rain that we have seen in some time. We had placed buckets on the glulams where we were concerned about drips. At one point, during the heavy 20 minute rain, the buckets were overflowing with water and creating lovely holes in the newly poured concrete. This may not have been as devasting if we were thinking, "hey, it's just the concrete, our hardwood/carpet/tile will cover all this." But, we are trying to minimize all finish work and were planning on staining the concrete. This rainsoaked and pocked floor was our finished floor. Roberto and friends never stopped working. They ended up staying until 4 p.m. and undid most of the rain damage AND didn't expect any extra payment. They actually said they would look forward to our next pour on a sunny day.
During the weeks after the pour, interior walls have been framed on the basement level, some framing has begun on the second level, lighting has been decided and John, our electrician, has ordered materials and begun wiring.
We (meaning Keith and the building crew) are feeling a bit of pressure to get the house "weathered in" prior to freezing weather. We have little control over this and I figure it will work out. In an effort to pretend like none of this is that stressful, I'm leaving on Wednesday, September 27 for Greece with my friends Barb and Alicia. I have no business going, but someone has.
I'll be out of commission for 10 days and then vow to update this more frequently.

1 Comments:

Anonymous Anonymous said...

It is remarkable to see on one day a pile of tubing, one day later a string of tubing installed trailing all over the place, then one day later - a neatly poured and finished concrete floor. All that work and no one can see it. I am pretty sure that no one has complained about the exposed steel on the ground floor, I have heard a number of rather loud complaints about people vacationing in Greece (I believe) while others are working their fingers to the bone.

2:33 PM  

Post a Comment

<< Home